Site 13, Zone 2, Booster Pump Station Upgrades

Newland Communities
Cotton Lane and Estrella Parkway, Goodyear, Arizona
  • Booster pump station upgrades
  • Hydraulic modeling and analysis

Based on a recommendation in the Water Master Plan developed by Entellus, there was a need to increase the capacity of a booster pump station within the community.

The original booster pump station had seven pumps ranging from 500gpm to 5000gpm. Our team replaced one of the smaller pumps with a 2,000gpm Variable Frequency Drive (VFD) pump and added an additional 2,000gpm pump. The design included the replacement of several valves, modifications to the pump sequence, Supervisory Control and Data Acquisition (SCADA) controls, electrical supply, as well as construction and commissioning support. In addition, we provided training for City personnel in the operation of the system under normal operating conditions and during certain emergency or failure scenarios.